Approval is sought for an access design associated with the Bramford to Twinstead electricity network project.
Bramford to Twinstead
Official description
Discharge of Requirements - Access Design AB-AP6 - Formal Submission as per Schedule 3, Requirement 11(1) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024
- Council
- Suffolk
- Reference
- SCC/0034/26/DoR
- Application type
- Discharge Of Requirements (Bramford To Twinstead)
- Status
- Application Approved
- Decision
- Permitted
- Submitted
- 24 Feb 2026
- Decision date
- 6 May 2026
More applications in Suffolk
Submission seeking advice on Requirement XX – Management Plan for Stage ZZ
Discharge of Requirement 36(1) Port Traffic, Lowestoft Port Construction Traffic Management Plan Sscoping Letter
Formal Submission, Schedule 3, Requirement 11(1) – Access Design AB-AP16 - STAGE 3.2
Formal submission In accordance with Requirement11(1) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024 (the Order), National Grid are formally submitting the…
Construction of a covered digestate storage lagoon, including associated underground pipeline, access track and ancillary infrastructure, to support the existing anaerobic…
Formal Submission - Requirement 11(1) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024 (the Order), we are formally submitting the access designs for E-DAP3…