Install 1.3 kilometres of overhead electricity line on 17 wooden poles, continuing underground to a new transmission substation.
Transmission DNO connection An Suidhe Substation
Trades this could involve
Official description
We propose to install a new overhead line spur to provide an electricity connection to a new transmission substation site. This will consist of 17 new wood poles not exceeding 13 meters in height in keeping with existing OHL, no poles being removed. OHL is 1300 meters in length with copper conductor and steel cross arms. For information, the line will move to underground cable from the final pole to meet the new development.
- Council
- Energy Consents Unit
- Reference
- ECU00006448
- Application type
- Screening
- Status
- Complete
- Decision
- Permitted
- Submitted
- 21 Jul 2026
- Decision date
- 30 Sep 2026
More applications in Energy Consents Unit
Proposed operation-only Section 36 application for Parcel B (Albusia), comprising approximately 400MW of the wider 456MW Gretna Green Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Rufusia), comprising approximately 100MW of the wider 300MW Mossmorran Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Flavusia), comprising approximately 300MW of the wider 342MW Kincardine Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Innerwick Storage), comprising approximately 170MW of the wider 650MW Braxbess and Innerwick Storage Battery Energy…
Installation of two terminal wood poles on the existing DG 132kV overhead line, including associated conductors and downleads.
The proposed development involves reconductoring an existing overhead line located at Brevig Harbour on the Isle of Lewis. The existing line comprises seven spans of 2x32 mm2 HD…