Install a short overhead electricity connection using one new single pole and two double poles near Onich.
Mast site at Tom Lain, Coir Na Coille, Onich, Fort William - 33kV Overhead Line
Trades this could involve
Official description
I am seeking consent for a new small section (2 spans) of 33kV overhead line which will connect onto an existing section of 33kV overhead line at new pole 185a to the east of the Glensheallach transformer, to the north east of the Onich area of Fort William. New single pole 185a will be installed on the existing overhead line and a back-stay will be installed for tee-off. From pole 185a, there will be a new 2 span overhead spur which will consist of two new double poles, with 2 supporting stay wires on pole 2.
- Council
- Energy Consents Unit
- Reference
- ECU00006444
- Application type
- Development
- Status
- Consultation
- Submitted
- 10 Jul 2026
More applications in Energy Consents Unit
Proposed operation-only Section 36 application for Parcel B (Albusia), comprising approximately 400MW of the wider 456MW Gretna Green Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Rufusia), comprising approximately 100MW of the wider 300MW Mossmorran Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Flavusia), comprising approximately 300MW of the wider 342MW Kincardine Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Innerwick Storage), comprising approximately 170MW of the wider 650MW Braxbess and Innerwick Storage Battery Energy…
Installation of two terminal wood poles on the existing DG 132kV overhead line, including associated conductors and downleads.
The proposed development involves reconductoring an existing overhead line located at Brevig Harbour on the Isle of Lewis. The existing line comprises seven spans of 2x32 mm2 HD…