Move an existing power-line pole slightly and add a three-pole branch with supporting stays.
Lands at Cairncatto, Longhaven, Peterhead, AB42 4YR.
Trades this could involve
Official description
Existing overhead 33kv line connecting Boddam from Strichen. At Pole 17 we are required to move the position slightly and add an additional 3 pole spur with two new stays.
- Council
- Energy Consents Unit
- Reference
- ECU00006438
- Application type
- Development
- Status
- Consented
- Decision
- Permitted
- Submitted
- 30 Jun 2026
- Decision date
- 30 Sep 2026
- Postcode
- AB42 4YR
More applications in Energy Consents Unit
Proposed operation-only Section 36 application for Parcel B (Albusia), comprising approximately 400MW of the wider 456MW Gretna Green Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Rufusia), comprising approximately 100MW of the wider 300MW Mossmorran Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Flavusia), comprising approximately 300MW of the wider 342MW Kincardine Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Innerwick Storage), comprising approximately 170MW of the wider 650MW Braxbess and Innerwick Storage Battery Energy…
Installation of two terminal wood poles on the existing DG 132kV overhead line, including associated conductors and downleads.
The proposed development involves reconductoring an existing overhead line located at Brevig Harbour on the Isle of Lewis. The existing line comprises seven spans of 2x32 mm2 HD…