A new 2 span overhead spur requires to be built in order to supply a mast site at Tom Lain, Coir Na Coille. The overhead apparatus will…
33kV Overhead Line - Tom Lain, Coir Na Coille, Onich, Fort William
Official description
A new 2 span overhead spur requires to be built in order to supply a mast site at Tom Lain, Coir Na Coille. The overhead apparatus will require Section 37 consent however it is just to the north of the Onich to North Ballachulish Woods SAC and the Onich to North Ballachulish Woods and Shore SSSI and so requires to be screened under Schedule 2 development. Note that the underground cable and free standing transformer pole are all permitted development and for additional information only. This application relates to the new overhead spur from pole 185a.
- Council
- Energy Consents Unit
- Reference
- ECU00006384
- Application type
- Screening
- Status
- Complete
- Decision
- Permitted
- Submitted
- 17 Apr 2026
- Decision date
- 25 Jun 2026
More applications in Energy Consents Unit
Proposed operation-only Section 36 application for Parcel B (Albusia), comprising approximately 400MW of the wider 456MW Gretna Green Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Rufusia), comprising approximately 100MW of the wider 300MW Mossmorran Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Flavusia), comprising approximately 300MW of the wider 342MW Kincardine Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Innerwick Storage), comprising approximately 170MW of the wider 650MW Braxbess and Innerwick Storage Battery Energy…
Installation of two terminal wood poles on the existing DG 132kV overhead line, including associated conductors and downleads.
The proposed development involves reconductoring an existing overhead line located at Brevig Harbour on the Isle of Lewis. The existing line comprises seven spans of 2x32 mm2 HD…