Construction and operation of a 132 kV overhead line to connect the Blarghour Wind Farm, situated approximately 7km north west of…
Blarghour Wind Farm 132 kV overhead line connection
Official description
Construction and operation of a 132 kV overhead line to connect the Blarghour Wind Farm, situated approximately 7km north west of Inveraray, to Creag Dhubh Substation which is located approximately 2.5 km south west of Cladich. This project replaces the previous project that underwent scoping in 2023/2024 under ECU Ref: ECU00005018.
- Council
- Energy Consents Unit
- Reference
- ECU00006383
- Application type
- Scoping
- Status
- Pre Application Complete
- Decision
- Permitted
- Submitted
- 15 Apr 2026
- Decision date
- 29 Jun 2026
More applications in Energy Consents Unit
Proposed operation-only Section 36 application for Parcel B (Albusia), comprising approximately 400MW of the wider 456MW Gretna Green Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Rufusia), comprising approximately 100MW of the wider 300MW Mossmorran Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Flavusia), comprising approximately 300MW of the wider 342MW Kincardine Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Innerwick Storage), comprising approximately 170MW of the wider 650MW Braxbess and Innerwick Storage Battery Energy…
Installation of two terminal wood poles on the existing DG 132kV overhead line, including associated conductors and downleads.
The proposed development involves reconductoring an existing overhead line located at Brevig Harbour on the Isle of Lewis. The existing line comprises seven spans of 2x32 mm2 HD…