Construction and operation of a new 132kV overhead line (OHL) connection between Shin Substation and a proposed cable sealing end (CSE)…
Shin to Loch Buidhe 132kV Overhead Line Rebuild
Official description
Construction and operation of a new 132kV overhead line (OHL) connection between Shin Substation and a proposed cable sealing end (CSE) compound approximately 2 km west of Loch Buidhe Substation, and the dismantling of the existing 132kV OHL connection between Shin Substation and Loch Buidhe Substation
- Council
- Energy Consents Unit
- Reference
- ECU00006257
- Application type
- Screening
- Status
- Complete
- Decision
- Permitted
- Submitted
- 12 Sep 2025
- Decision date
- 10 Dec 2025
More applications in Energy Consents Unit
Proposed operation-only Section 36 application for Parcel B (Albusia), comprising approximately 400MW of the wider 456MW Gretna Green Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Rufusia), comprising approximately 100MW of the wider 300MW Mossmorran Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Flavusia), comprising approximately 300MW of the wider 342MW Kincardine Battery Energy Storage System (BESS), granted…
Proposed operation-only Section 36 application for Parcel B (Innerwick Storage), comprising approximately 170MW of the wider 650MW Braxbess and Innerwick Storage Battery Energy…
Installation of two terminal wood poles on the existing DG 132kV overhead line, including associated conductors and downleads.
The proposed development involves reconductoring an existing overhead line located at Brevig Harbour on the Isle of Lewis. The existing line comprises seven spans of 2x32 mm2 HD…