Proposed Construction and Operation of a Strategic Electricity Transmission Hub Consisting of a 400kV AC Substation, an HVDC Converter…

HVDC Converter Station Arnish Isle Of Lewis

Official description

Proposed Construction and Operation of a Strategic Electricity Transmission Hub Consisting of a 400kV AC Substation, an HVDC Converter Station, and the Associated Undertaking of Earthworks, the Formation of Platforms, Landscaping, Means of Access, Means of Enclosure, Site Drainage, Temporary Construction Compounds, Peatland Reinstatement and Improvement and Other Associated Operations (National Development)

Council
Western Isles
Reference
25/00061/PPPM
Application type
Planning Permission In Principle Maj-Nat
Status
Decided
Decision
Conditions
Submitted
28 Feb 2025
Decision date
28 Nov 2025